Dear BCOE Colleagues:

Some of you have mentioned irregular temperatures in Bourns Hall B-wing.  Fan room work on HVAC fans continues this week along with fine tuning of the new exhaust fans on the roof.  As this is progressing, air balance teams are also working to program and balance the many new variable air fume hood valves.  All of this combines to create rather irregular room temperatures in the B-wing.

Work on the first floor East side fan room is occurring today and tomorrow.  The work in the second floor East fan room will follow, and lastly the second floor West fan room replacements will be done.

I appreciate your continued patience as the last phase of the renovation project continues.  Please let me know if you have questions.

Maggie
Safety and Facilities Coordinator
Bourns College of Engineering
University of California, Riverside
Tel: 951-827-1241
Fax: 951-827-3188
Three words for life from SuperKenny: Honesty, Respect, Gratefulness