Dear BCOE Colleagues:

Drain line capacity must be increased in order to accommodate new wet labs in Bourns B-wing second floor.  

Contractors will be removing concrete, trenching, and adding pipe along the first floor exterior corridor, north (patio) side of B-wing beginning Wednesday and will be working for approximately two weeks.

Important information and dates are noted below.  Please let me know if you have questions.

Maggie

 

  • MONDAY, OCTOBER 3rd – concrete saw-cutting will begin:
    • In front of B-134 and the west double door leading to the main breezeway beginning between 4:00 – 6:30 am and concluding approximately 8:00 am.
    • In front of the east double door leading to the main breezeway and up to but NOT in front of the B-136 doorway beginning at approximately 8:00 am and concluding at 11:00 am
    • MONDAY, OCTOBER 3rd and TUESDAY, OCTOBER 4th
      • Signage notifying pedestrians of upcoming detours will be posted
      • Course instructors for classes in B-164, B-108, and B-134 are asked to please let students know that access must be via the second floor stair or elevator
      • WEDNESDAY, OCTOBER 5th through WEDNESDAY, OCTOBER 19th
        • Signage will remain
        • Pedestrian will be required to use detours
        • Ditch digging and pipe installation/replacement/tie-in will commence

Safety and Facilities Coordinator
Bourns College of Engineering
University of California, Riverside
Tel: 951-827-1241
Fax: 951-827-3188